An 11-day shipment slip that never happened
The mill was meeting its rolling plan 100%, but acceptance lagged: by week six, 12% of the order was rolled but not accepted. The bottleneck was a single test-specimen machining centre. We agreed two shifts for the laboratory and sampling at the mill exit; the backlog was cleared in 19 days and the order ran with a buffer of certified stock.